Construction Updates
Shasta Elementary School Update
Construction crews are working hard at Shasta Elementary to meet their completion date of summer 2019. This $18 million project (funded by Measure K & Developer Fees) is much needed for the growing population in the Shasta Elementary neighborhood.
Project Background
The project consists of the following:
- Addition of five new classroom buildings including a new Kindergarten complex
- Addition of administration building
- Repurposing of existing administration building into regular classroom
- Renovation of old library space into new library space
- Site work including demolition, utilities, new bus drop off, parking, playground, concrete, drainage and landscaping
Take a Tour
Take a Tour
Project Details - Updated 8/13/19
A. When:
a. Schedule:
i. Work Commenced on: November 2017
ii. Scheduled Completion: Now
B. Who:
a. Architect & Designer: Lionakis Architects, Sacramento
b. Contractor: United Building Contractors, Chico
C. What:
a. Background: Three phased construction project, we are completing the project before school starts.
i. The scope of this project included the addition of five new classroom buildings a new administrative office and an extension of the existing main parking lot.
ii. Construction Cost: $14M.
iii. Funding: Developer fees